London Borough of Brent · Ealing Road (A4089), Wembley HA0 4LL · 2026
By Tom Jackson, Production Lead
The brief
Brent wanted the Piccadilly line bridge on Ealing Road repainted with a designed mural and a protective finish. The bridge belongs to Transport for London and sits directly above the running line between Alperton and Park Royal. Nothing could fall onto the railway and nobody could cross the boundary fence.
What we did
Took the RAMS through six revisions with TfL Infrastructure Protection, written to TfL standards G0023 and T0005. The final version was issued on 9 July 2026.
Secured the highways permit and a Section 61 noise consent from Brent for night working.
Worked overnight, 22:00 to 05:00, under a single-lane closure with shuttle signals run by ACE Highways. A TfL inspector was on site.
Cleared vegetation by hand, removed the pigeon spikes, and prepared steel and concrete with hand tools only. No power tools, no washing.
Applied an isolating primer and Dacrylate Margard Easyclean AGS 300-LINE pigmented anti-graffiti finish to both elevations, from a scissor lift supplied by Star Platforms.
Fitted two pre-printed Alupanel artworks, a kingfisher and a peacock, into the brick reveals, then reinstated the spikes. Both panels were co-designed and chosen. The bridge artwork itself was applied to TfL standards for its bridges.
Finished on site on Friday 18 September 2026.
Who was involved
London Borough of Brent (client). Transport for London (asset owner). Matt Hopkins, Group 19 (artwork design). ACE Highways (traffic management). Star Platforms (access). Dacrylate (coatings). Works in Public (principal contractor, RAMS, painting and installation).
What the client got
A repainted bridge with a finish that can be cleaned of graffiti, approved by the asset owner, with one lane open to traffic throughout.